This case study documents a field cable fault test carried out for a large photovoltaic (PV) power generation project in Northwest China. A 35 kV collector feeder cable suffered a flashover-type sealed fault, and the owner needed an accurate fault distance and the exact excavation point before repairs could begin. The following sections summarise the background, field conditions, test equipment and the workflow used to locate and verify the fault.
| Project type | 300 MW photovoltaic power generation project, Northwest China |
| Test date | December 2023 |
| Cable rating | 26/35 kV, YJLV, 3 * 300 mm² |
| Fault type | Flashover-type sealed fault (Phase A) |
| Task scope | Fault distance measurement (prelocation) + precise pinpointing |
No fault discharge sound was detected at the intermediate joint manholes located before and after the prelocated position. Using the Model 503D pinpointing instrument, a clear but faint discharge sound was heard around the 320 m position; the signal was weak — likely dispersed by sand — and there was no obvious ground vibration. After excavation no visible external damage was found, but on re-pressurising the cable one spot showed markedly stronger vibration, confirming the fault point. Opening the cable confirmed a single-phase joint within the cable body itself. The cable was then repaired.
After repair, the AC withstand test was repeated on the cable. It passed at 52 kV for 60 minutes, confirming the cable was restored to a healthy operating condition.
Note: For privacy protection, all specific place names, substation/feeder identifiers and personnel names in the original report have been removed or generalised in this published version.